54 

 

Actors: MDFG, PSC, independent consultants, NGOs, PAPs. 



The MDFG will organize project  completion workshops  with  government  agencies, NGOs and 

representatives of PAPs after completion of the expropriation/compensation operations but prior 

to  the  closure  of  the  mitigation  measures.  The  aim  of  that  exercise  is  to  assess  progress  in  the 

operations executed, suggest corrective measures where needed and solve pending issues. After 

completion of all expropriation/compensation operations, PAPs will be consulted in a household 

survey.  The  aim  of  that  survey  is  to  assess  the  impacts  of  the  social  mitigation  measures 

implemented.  Likewise,  rural  communities  with  PAPs  will  be  consulted  to  provide  their 

assessments of the impacts of the social mitigation measures applied. 

The findings of the survey and the workshops will be presented in the project completion report, 

which will be established by the MDFG. 

This RAP in Georgian will be disclosed on the MDFG website and at MDFG office before Project 

appraisal.  The  RAP  in  Georgian  will  also  be  disclosed  to  the  APs  at  the  relevant  Municipality 

office (Gamgebeli) and at village administration (Sacrebulo) once subprojects are identified. Its 

English version will be disclosed on the WB website prior to Project appraisal and after the RAP 

is endorsed by the Executing Agency (EA) which will be MDFG in this case. Once a RAP for a 

subproject  has  been  prepared  and  approved  by  MDFG  and  WB  it  will  be  disclosed  at  relevant 

Sacrebulo office (Gamgeoba and at village administration (Sacrebulo). A pamphlet in Georgian, 

summarizing compensation eligibility and entitlement provisions, will be sent to all AP/AFs before 

the initiation of the compensation/rehabilitation process and before signing contract awards. The 

consultation process will be continued throughout the project cycle. 



 

 


55 

 

9. Costs and Financing  



9.1. Introduction  

The  presumable  costs  of  resettlement  within  the  scope  of  the  subproject  to  build  a  tourist 

infrastructure on the territory adjacent to the Ananuri Complex cover the compensation amounts 

for temporal and/or permanent suspension of business.  

MDF,  as  the  project  owner,  is  responsible  for  timely  allotting  the  finances  to  realize  the 

Resettlement Policy. The correctness of distribution of the finances must be checked twice a year 

based  on  the  budget  requirements  fixed  with  the  Resettlement  Action  Plan  (RAP).  The 

compensation and rehabilitation budget must be immediately paid by the Municipal Development 

Fund of Georgia.  

9.2 Detailed Budget 

In the following section, you will find the calculations of various types of compensation and aids 

based  on  the  Entitlement  Matrix.  The  RAP  gives  the  minimum  amounts  of  compensations. 

However, the amendments can be made during the meetings to be held before signing the contract.  

Following the above- mentioned, we can consider the following groups in the project zone:  

1. 


7 APs running the business adjacent to the project zone, 2-20 m from it.  

2. 


8 APs as hired employees.  

3. 


15 APs renting the territory and running business in the project zone.  

4. 


12 APs running informal business in the project zone.  

As already mentioned, the representatives of Dusheti Municipality reviewed the wishes  of APs 

and  decided  to  maintain  business  for  all  APs  both,  in  the  construction  and  operation  phases. 

Consequently, none of the APs will lose his business within the scope of the project.  

An expected impact implies the reduction of income because the accomplishment of the works 

may hamper the movement of tourists across the project zone. The total suspension of business is 

not planned at the stage of the project implementation; however, following the experience with the 

previous similar projects, the compensation for total suspension of business was envisaged as a 

part of the compensation amounts.  

Within the scope of the present subproject, no purchase of land, buildings and premises, annual 

perennial plantings or harvest compensation is envisaged.  

Within  the  scope  of  the  project,  only  the  compensations  for  hampering  and/or  suspending  the 

business and inventory transportation, as well as vulnerability compensation will be given out.  

 

 

 



56 

 

 9.2. Methods to Calculate Compensations 



9.2.1. Reduction in Incomes  

For the projects of a similar type financed by the World Bank, the methods to calculate the income 

reduction have been developed. The methods given below were used for the subprojects realized 

within the scope of RDP I (Telavi, Kvareli). The methods used in this period were agreed both, 

with the World Bank and the Government of Georgia.  

As per the developed methods, a legal or private entity, being a business owner, was to be given 

20% of the profit gained in the previous years. In addition, the said entity was allowed to run his 

business non-stop in the project zone. The profit of the previous years was calculated based on the 

official document submitted by the business owner – a Tax Declaration. If the entity had informal 

business or was not a tax-payer (mini-entrepreneur), 20% of profit was calculated by considering 

the subsistence minimum fixed for a 5-member family. At present, the subsistence minimum for a 

family of 5 is fixed at 338.3 GEL. In case the official profit of a legal entity is less than 338.3 GEL, 

the same amount will be considered as his profit and his due compensation will be calculated based 

on 338.3 GEL.  

In addition, the principle of seasonality was taken into account in calculating the compensation 

amounts


 for one company (who provided official Tax declaration). Based on the information 

provided by the local people, the number of tourists to the Ananuri Complex is 2.5-3 times more 

in summer than in winter. Nearly the same information was received from Dusheti Municipality.  

Consequently, the annual profit presented by a legal entity, was distributed among the seasons as 

follows:  if  considering  that  business  receives  X  part  of  the  annual  income,  then  its  income  in 

summer and autumn will be 2X and 3X in spring. Consequently, if the profit of a legal entity was 

7000 GEL a year, the profit of this entity will be calculated as follows: 7000:7X3, equaling to 3000 

GEL in the given case.  

The  unit  compensation  rates  will  be  assessed  by  Project  consultant  or  by  the  MDF  authorized 

independent  evaluator  on  clear  and  transparent  methodologies  acceptable  to  WB.  The  assessed 

compensation rates will then be verified and certified by the Environmental and Resettlement Unit 

of MDFG. 

Table 16: Compensation Entitlement Matrix 

Type of Loss 

Application 

Number of Aps 

Compensation 

Entitlements 

Loss of Income and Livelihood 

Temporary 

reduction of 

incomes 


Formal and informal 

PAP’s in project area 

26 PAP 

PAP’s will be given 



20% of profit. The 

profit will be 

calculated by 

considering the 

subsistence minimum 

fixed for a 5-member 




Yüklə 0,7 Mb.

Dostları ilə paylaş:
1   ...   17   18   19   20   21   22   23   24   ...   28




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə