Guidance Manua pdf



Yüklə 0,58 Mb.
Pdf görüntüsü
səhifə23/24
tarix25.05.2018
ölçüsü0,58 Mb.
#45844
1   ...   16   17   18   19   20   21   22   23   24

 

56

0



20

40

60



80

100


120

A-99 N-99 F-00 M-00 A-00 N-00 F-01 M-01 A-01 N-01 J-02 M-02

MIB Concentration (ng/L)

R8

R9A



R9B

R10


0

10

20



30

40

50



60

70

80



A-99

N-99


F-00

M-00


A-00

N-00


F-01

M-01


A-01

N-01


J-02

M-02


MIB Concentration (ng/L)

R13


R14

R16


290 

ng/L


that fall.  MIB concentrations were somewhat higher in the CAP canal between 

September and November of 2001 due to MIB coming from the Colorado River (15 

ng/L), but not from Lake Pleasant.  MIB concentrations in the Arizona canal were 

maintained at < 30 ng/L at Squaw Peak WTP.  Switching production from Deer Valley 

WTP to Union Hills WTP prevented any necessity to treat high MIB concentrations in 

water that would have otherwise reached Deer Valley WTP                                                                                                                                                                                     

(Figure 7-2). 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

Figure 7-1.  MIB in Salt River cluster (Saguaro Lake) from August 1999 through March 2002. 

 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



Figure 7-2.  MIB in Arizona canal (SRP cluster) from August 1999 through March 2002.  MIB in January 

2002 (R16) was 290 ng/L. 

 



 

57

7.3  CASE STUDY #2 - HIGH MIB "HOT SPOT" ALONG ARIZONA CANAL 

 

7.3.1  Process Control Monitoring 

Throughout June and early July of 2001 significant production of MIB was observed in 

the Arizona Canal between Squaw Peak WTP and Deer Valley WTP, a distance of 

roughly 10 miles along the canal (Figure 7-3).   

 

0

10



20

30

40



50

60

70



80

90

100



0

5

10



15

Distance (miles)

MIB (ng/L)

MIB-(6/26/01)

MIB-(7/3/01)

MIB-(7/8/01)

 

Figure 7-3.  Increasing MIB along the Arizona Canal between Squaw Peak and Deer Valley WTPs



 

 

To determine the exact amount of MIB produced in the canal over time, Figure 7-4 was 



developed. It shows the MIB production between  these two WTPs.  Net MIB production 

was calculated as MIB concentration of raw water at Deer Valley WTP minus MIB 

concentration of raw water at Squaw Peak WTP. 



 

58

-20



0

20

40



60

80

100



Net Change in MIB (ng/L)

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

 



 

 

Figure 7-4.  Calculated net production of MIB in Arizona Canal between Squaw Peak and Deer Valley 



WTPs, by month, before, during and after canal brushing and copper application. 

7.3.2  Diagnosis 

Based upon Figures 7-3 and 7-4 it was obvious that MIB was being produced in this 

section of the canal.  SRP was contacted as to the pumping status of groundwater wells 

located around Central Avenue.  We were informed that the wells which contained 

nitrate were in fact being operated (Well #12.5E13.1N has 12.6 mg NO

3

-N/L; Well 



#12E13.3N had 7.0 mg NO

3

-N/L).  However the wells could not be turned off due to 



downstream water demands and lack of hydraulic capacity in the upper Arizona Canal 

to convey more surface water. 

 

7.3.3  Treatment Selection 

The canal management “toolbox” included several options, each of which are described 

for the above scenario: 

 

1. 



Reduce nitrate input into canal from groundwater pumping.  Based upon 

discussions with SRP this was not deemed feasible due to lack of surface water 

supplies (drought period) in conjunction with limited hydraulic capacity at  the head 

of the Arizona canal for increased flow of surface waters.  Nitrate-rich groundwater 

could not be diverted, and was probably a factor for the MIB production in this 

section of canal. 

 

Cu 


2+

 on 7/9-10 

at 7th street 

Canal  


brushing

 

Cu 



2+

 on 8/24 

at 56th street 

Jul           Aug             Sep            Oct           Nov 

Canal brushing: 8/1-2/01 (24th St - Central); 8/14-17/01 (24th St - 29th Ave) 

(Net change in MIB = MIB at 29th Ave - MIB at 24th St.) 



 

59

2. 



Mechanically remove periphytic (attached) algae from canal walls. Mechanical 

brushing of canal walls was deemed feasible.  Visual observations of the canal 

indicated a 3 to 6 cm thick mat of attached (periphytic) algae on the sides of the 

canal.  SRP was contacted to schedule mechanical brushing.  An approximately  2-

week lead time was required. 

 

3. 



Apply liquid biocides to canal water.  Liquid copper addition was considered 

feasible for control of attached algae.  It would be preferable to add copper after 

mechanical brushing removed dense algae from the canal walls.  Copper would 

treat the walls and bottom of the canal. 

 

4. 


Apply fixed biocides to canal walls during canal dry-up. This option was only 

deemed feasible during canal dry-up (December to January), so this option was 

not implemented. 

 

5. 



Shift finished water production to WTP with lower T&O levels.  Deer Valley WTP 

was scheduled for a construction plant shut-down in September 2001, and had to 

be on-line during part of July 2001 for quarterly regulatory monitoring.  After 

discussions with City of Phoenix water production staff it was decided that Union 

Hills WTP on the CAP Canal could increase production earlier and allow Deer 

Valley WTP to go off-line sooner.  This would decrease the number of days Deer 

Valley WTP had to operate, and treat water with potentially high MIB levels.  This 

option was implemented. 

 

7.3.4  Treatment Application 

Several treatment options were implemented.  Mechanical brushing was conducted on 

July 19-21, August 1-2 and again on August 14-17.  Copper addition was applied 

between Squaw Peak and Deer Valley WTPs on July 10, 2000, at 7

th

 Street for 6 to 8 



hours.  Copper was also applied above Squaw Peak WTP throughout August and 

October (56

th

 Street and Beeline Highway) to address MIB “hot spots” further upstream.  



Copper residuals of 0.3 to 0.7 ppm were monitored for 5 to 7 miles downstream of the 

copper application point.  Reductions in attached (periphytic) algae biomass indicated 

that both copper and brushing were effective for the duration of the application (2 to 3 

weeks).  Switching of water production to Union Hills WTP also proved very effective. 

 

7.3.5  Follow-up Monitoring 

Figure 7-4 shows that after implementation of in-canal treatments the MIB production in 

the Arizona Canal between Squaw Peak and Deer Valley WTPs was maintained at < 5 

ng/L.  Later in the summer, as Deer Valley WTP production was shifted to other City of 

Phoenix WTPs, no further canal treatments along that section were implemented.  MIB 

production in the canal increased again, but had no impact on the City of Phoenix’s 

water treatment plants.  A combination of in-canal treatments and shifting production 

was effective at minimizing MIB levels entering the WTPs. 

  



Yüklə 0,58 Mb.

Dostları ilə paylaş:
1   ...   16   17   18   19   20   21   22   23   24




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə