56
0
20
40
60
80
100
120
A-99 N-99 F-00 M-00 A-00 N-00 F-01 M-01 A-01 N-01 J-02 M-02
MIB Concentration (ng/L)
R8
R9A
R9B
R10
0
10
20
30
40
50
60
70
80
A-99
N-99
F-00
M-00
A-00
N-00
F-01
M-01
A-01
N-01
J-02
M-02
MIB Concentration (ng/L)
R13
R14
R16
290
ng/L
that fall. MIB concentrations were somewhat higher
in the CAP canal between
September and November of 2001 due to MIB coming from the Colorado River (15
ng/L), but not from Lake Pleasant. MIB concentrations in the Arizona canal were
maintained at < 30 ng/L at Squaw Peak WTP. Switching production from Deer Valley
WTP to Union Hills WTP prevented any necessity to treat high MIB concentrations in
water that would have otherwise reached Deer Valley WTP
(Figure 7-2).
Figure 7-1. MIB in Salt River cluster (Saguaro Lake) from August 1999 through March 2002.
Figure 7-2. MIB in Arizona canal (SRP cluster) from August 1999 through March 2002. MIB in January
2002 (R16) was 290 ng/L.
57
7.3 CASE STUDY #2 - HIGH MIB "HOT SPOT" ALONG ARIZONA CANAL
7.3.1 Process Control Monitoring
Throughout June and early July of 2001 significant production of MIB was observed in
the Arizona Canal between Squaw Peak WTP and Deer Valley WTP, a distance of
roughly 10 miles along the canal (Figure 7-3).
0
10
20
30
40
50
60
70
80
90
100
0
5
10
15
Distance (miles)
MIB (ng/L)
MIB-(6/26/01)
MIB-(7/3/01)
MIB-(7/8/01)
Figure 7-3. Increasing MIB along the Arizona Canal between Squaw Peak and Deer Valley WTPs
To determine the exact amount of MIB produced in the canal over time, Figure 7-4 was
developed. It shows the MIB production between these two WTPs. Net MIB production
was calculated as MIB concentration of raw water at Deer Valley WTP minus MIB
concentration of raw water at Squaw Peak WTP.
58
-20
0
20
40
60
80
100
Net Change in MIB (ng/L)
Figure 7-4. Calculated net production of MIB in Arizona Canal between Squaw Peak and Deer Valley
WTPs, by month, before, during and after canal brushing and copper application.
7.3.2 Diagnosis
Based upon Figures 7-3 and 7-4 it was obvious that MIB was being produced in this
section of the canal. SRP was contacted as to the pumping status of groundwater wells
located around Central Avenue. We were informed that the wells which contained
nitrate were in fact being operated (Well #12.5E13.1N has 12.6 mg NO
3
-N/L; Well
#12E13.3N had 7.0 mg NO
3
-N/L). However the wells could not be turned off due to
downstream water demands and lack of hydraulic capacity in the upper Arizona Canal
to convey more surface water.
7.3.3 Treatment Selection
The canal management “toolbox” included several options, each of which are described
for the above scenario:
1.
Reduce nitrate input into canal from groundwater pumping. Based upon
discussions with SRP this was not deemed feasible due to lack of surface water
supplies (drought period) in conjunction with limited hydraulic capacity at the head
of the Arizona canal for increased flow of surface waters. Nitrate-rich groundwater
could not be diverted, and was probably a factor for the MIB production in this
section of canal.
Cu
2+
on 7/9-10
at 7th street
Canal
brushing
Cu
2+
on 8/24
at 56th street
Jul Aug Sep Oct Nov
Canal brushing: 8/1-2/01 (24th St - Central); 8/14-17/01 (24th St - 29th Ave)
(Net change in MIB = MIB at 29th Ave - MIB at 24th St.)
59
2.
Mechanically remove periphytic (attached) algae from canal walls. Mechanical
brushing of canal walls was deemed feasible. Visual observations of the canal
indicated a 3 to 6 cm thick mat of attached (periphytic) algae on the sides of the
canal. SRP was contacted to schedule mechanical brushing. An approximately 2-
week lead time was required.
3.
Apply liquid biocides to canal water. Liquid copper
addition was considered
feasible for control of attached algae. It would be preferable to add copper after
mechanical brushing removed dense algae from the canal walls. Copper would
treat the walls and bottom of the canal.
4.
Apply fixed biocides to canal walls during canal dry-up. This option was only
deemed feasible during canal dry-up (December to January), so this option was
not implemented.
5.
Shift finished water production to WTP with lower T&O levels. Deer Valley WTP
was scheduled for a construction plant shut-down in September 2001, and had to
be on-line during part of July 2001 for quarterly regulatory monitoring. After
discussions with City of Phoenix water production staff it was decided that Union
Hills WTP on the CAP Canal could increase production earlier and allow Deer
Valley WTP to go off-line sooner. This would decrease the number of days Deer
Valley WTP had to operate, and treat water with potentially high MIB levels. This
option was implemented.
7.3.4 Treatment Application
Several treatment options were implemented. Mechanical brushing was conducted on
July 19-21, August 1-2 and again on August 14-17. Copper addition was applied
between Squaw Peak and Deer Valley WTPs on July 10, 2000, at 7
th
Street for 6 to 8
hours. Copper was also applied above Squaw Peak
WTP throughout August and
October (56
th
Street and Beeline Highway) to address MIB “hot spots” further upstream.
Copper residuals of 0.3 to 0.7 ppm were monitored for 5 to 7 miles downstream of the
copper application point. Reductions in attached (periphytic) algae biomass indicated
that both copper and brushing were effective for the duration of the application (2 to 3
weeks). Switching of water production to Union Hills WTP also proved very effective.
7.3.5 Follow-up Monitoring
Figure 7-4 shows that after implementation of in-canal treatments the MIB production in
the Arizona Canal between Squaw Peak and Deer Valley WTPs was maintained at < 5
ng/L. Later in the summer, as Deer Valley WTP production was shifted to other City of
Phoenix WTPs, no further canal treatments along that section were implemented. MIB
production in the canal increased again, but had no impact on the City of Phoenix’s
water treatment plants. A combination of in-canal treatments and shifting production
was effective at minimizing MIB levels entering the WTPs.