Inaugurated: 2nd December 2005



Yüklə 11,39 Mb.
tarix30.10.2018
ölçüsü11,39 Mb.
#76709



Inaugurated: 2nd December 2005

  • Inaugurated: 2nd December 2005

  • Completed: 15th August 2006



Meet drinking water needs of Bandh village

    • Meet drinking water needs of Bandh village
    • Develop and protect natural springs for drinking water
    • Recharge ground water and the natural spring to continue to provide potable water
    • Rain water harvest and conservation
    • Improve environment


A check dam with 506,000 litre storage capacity was constructed in a stream.

  • A check dam with 506,000 litre storage capacity was constructed in a stream.

  • 2 natural springs were developed and protected from animals.

  • Retaining walls were erected at strategic places

  • One earthen tank (percolation tank) for animals and ground water recharge was developed.



180 m3 of stone works were constructed for gully plugging

  • 180 m3 of stone works were constructed for gully plugging

  • 3 animal troughs were constructed

  • One filter chamber was developed for water filtration

  • 200 trees were planted in the project area

  • Piped water was supplied to villagers



Regular supply of drinking water to villagers of Bandh village and RUCHI complex and animals of 3 villages.

  • Regular supply of drinking water to villagers of Bandh village and RUCHI complex and animals of 3 villages.

  • In the long run the project will favourably impact:

    • Community health
    • Farm income
    • Local environment
    • Quality of lives of people


Total expenses - 7,54,124

  • Total expenses - 7,54,124

  • Total Grants-in-aid approved- 6,48,540

  • (USD 14,412 USD x INR 45)

    • Funds received to date - 2,70,034
    • Funds committed (not yet released)- 3,64,410
    • Loss due to exchange rate
    • fluctuation & bank commissions - 14,096
  • Deficit (754124-648540+14096) - 1,19,680



Check Dam - 9,21,485.00

  • Check Dam - 9,21,485.00

  • Spring Development - 72,595.00

  • Filter Chamber - 5,825.00

  • Distribution Tank - 17,257.00

  • Animal troughs - 7,183.00

  • Percolation tank - 56,607.00

  • Gully Plugging - 54,000.00

          • ---------------------------
          • 11,34,952.00








Height to the top : 6.13 meters

  • Height to the top : 6.13 meters

  • Height up to spillway level : 5.18 meters

  • Breadth at spillway level : 1.92 meters

  • Breadth at the plinth level : 6.51 meters

  • Capacity of the dam : 5,06,000 liters



































We are thankful to the following Rotary Clubs for

  • We are thankful to the following Rotary Clubs for

  • extending financial assistance to the project:

  • Rotary Club of Port Nicholson, New Zealand (International Cosponsor)

  • Rotary Club of New Plymouth West, New Zealand

  • Rotary Club of Milson, New Zealand

  • Rotary Club of Kasauli, India (Host Cosponsor)

  • The Rotary Foundation (India and USA offices)



Project Monitoring Committee comprising of

  • Project Monitoring Committee comprising of

  • Mrs. Jean Phipps for making all efforts to get the project going

  • Mrs. Barbara Williams, past District Governor, District 9940

  • Mr. Dharamvir Singh, Executive Director, RUCHI

  • Mr. Nagender Chauhan and Mr. Vinod Chauhan of RUCHI for coordinating the project execution

  • All members of RUCHI and Rotary Club of Kasauli for extending their fullest cooperation