Uzbekistan Doing Business 2020



Yüklə 1,75 Mb.
Pdf görüntüsü
səhifə11/64
tarix29.05.2023
ölçüsü1,75 Mb.
#114095
1   ...   7   8   9   10   11   12   13   14   ...   64
UZB

Indicator
Uzbekistan
Europe & Central
Asia
OECD high
income
Best Regulatory
Performance
Procedures (number)
17
16.2
12.7
None in 2018/19
Time (days)
246
170.1
152.3
None in 2018/19
Cost (% of warehouse value)
3.0
4.0
1.5
None in 2018/19
Building quality control index (0-15)
11.0
12.1
11.6
15.0 (6 Economies)
Uzbekistan
Doing Business 2020
Page 10


Figure – Dealing with Construction Permits in Uzbekistan – Procedure, Time and Cost
This symbol is shown beside procedure numbers that take place simultaneously with the previous procedure.
*
Note: Online procedures account for 0.5 days in the total time calculation. For economies that have a different procedure list for men and women, the graph shows the
time for women. For more information on methodology, see the
website (
). For details on the procedures
reflected here, see the summary below.
Doing Business
http://doingbusiness.org/en/methodology
Procedures (number)
1
2
* 3
4
5
6
7
8
9
* 10
11
12
13
14
15
16
17
0
50
100
150
200
Time (days)
0
0.5
1
1.5
2
2.5
3
Cost (% of warehouse value)
Time (days)
Cost (% of warehouse value)
Uzbekistan
Doing Business 2020
Page 11


Figure – Dealing with Construction Permits in Uzbekistan and comparator economies – Measure of Quality
Uzbekistan
Kazakhstan
Kyrgyz
Republic
Moldova
Russian
Federation
Europe
&
Central
Asia
0
2
4
6
8
10
12
14
16
Index score
11.0
13.0
11.0
12.0
14.0
12.1
Details – Dealing with Construction Permits in Uzbekistan – Procedure, Time and Cost
No.
Procedures
Time to Complete
Associated Costs
1
Request and obtain land clearance from Tashkent City Hokimiyat (submission of an
application for a land plot and of approved materials)
: District Governor's Office
Agency
Starting on January 1, 2016, the government changed the way land plots of up to 1 hectare are
allocated to legal entities and individuals. Land plots are now assigned on the basis of a
competitive selection process. Local authorities (municipalities) select land plots that are available
for allocation. Then, each Municipality has the local Department of Architecture and Construction
obtain all preliminary approvals of land allocation (previously separate procedures) from the
relevant authorities, depending on the environmental, architectural and zoning requirements of the
individual plots. Once all approvals are obtained internally by the Department of Architecture and
Construction, a complete set of documents is prepared for each land plot and submitted to the
contest organizer within the Municipality.
The time is 38 days (30 days after announcement is made to apply + 3 days for the committee to
evaluate the bids + 5 days to announce the decision).
Per the new process, an announcement is made in the mass media that there are land plots
allocated for a specific type of construction (e.g., kindergarten, produce store, a warehouse etc.).
Subsequently, these land plots, with all the necessary characteristics, are made available on the
website of the State Committee of Uzbekistan on Architecture and Construction:
http://1kms.uz/kms/announcementnew/list/11.
There is only one committee that organizes the bid. The announcement about the bid is made 1
month before the start of the bidding process, so bidders have 1 month to prepare the application
and submit the bid. The committee takes 3 days to evaluate all the bids and then it has 5 days to
announce the allotment decision.
Once the decision is made, it is announced in mass media (in the same national and local
newspapers where the bid was announced in the first place). The committee will inform the
winners within 2 days after the official announcement. Those who were not selected will find out in
the papers and on the website. The announcement is also sent by mail to all bidders.
The announcement of the auction / competition is made only 2 times a year (May and November).
This announcement is determined based on demand and supply of available land plots.
The Hokimiyat signs a contract with the winner and the winner can go ahead and sign a contract
with the project design company.
38 days
no charge
2

Yüklə 1,75 Mb.

Dostları ilə paylaş:
1   ...   7   8   9   10   11   12   13   14   ...   64




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə