`Code
1 -
Accepted
Uncontrolled when printed
INTERNAL INFORMATION
Northern Extension of Northolt Tunnel SIFT Report
Northern Extension of Northolt Tunnel SIFT Report
C222-ATK-DS-REP-020-000034
Revision – P06
Page 43
Uncontrolled when printed
INTERNAL INFORMATION
Location:
Colne Valley
Option name and description:
Community Forum Request for Northolt Tunnel Extension
OPTIONS CONSIDERED:
A
B
C
OPTION DESCRIPTION
Proposed Scheme
Tunnel with Heathrow Spur Provision
Tunnel without Heathrow Spur Provision
Headings
Appraisal criteria
QUALITATIVE IMPACT ASSESSMENT
and/or QUANTITIVE ASSESSMENT
RATIN
G
QUALITATIVE IMPACT ASSESSMENT
and/or QUANTITIVE ASSESSMENT
RATIN
G
QUALITATIVE IMPACT ASSESSMENT
and/or QUANTITIVE ASSESSMENT
RATIN
G
HS2 Operation
Feasibility - Passengers
Assess Passenger Dispersal covering road
(right of way), rail and public transport
N/A
0
N/A
0
N/A
0
Demand
Likely Relative Passenger Numbers
Likely Journey Times
Likely Demand
N/A
0
Slightly increased journey times due to tunnelled alignment and
Heathrow spur turnouts.
-
Slightly increased journey times due to tunnelled alignment.
-
Costs
Estimated whole life cycle costs to give
relative assessment
N/A
0
Excavated material management, operation and maintenance, all
likely to be significantly higher cost.
---
Excavated material management, operation and maintenance, all
likely to be significantly higher cost.
---
Estimated initial capital costs to give
relative assessment (The capital costs
include construction, land and
compensation costs)
N/A
0
Excavated material management, operation and maintenance, all
likely to be significantly higher cost. Procurement of TBMs will incur
a high cost. Cost estimate: additional £215.0 million.
---
Excavated material management, operation and maintenance, all
likely to be significantly higher cost. Procurement of TBMs will incur
a high cost. Cost estimate: additional £185.1million.
---
Environment
Input from ENVIRONMENTAL APPRAISAL
MATRIX
See separate environmental assessment
0
See separate environmental assessment.
+++
See separate environmental assessment
+++
Safety
Assess the relative safety during
construction,
Safety risks associated with viaduct – working at height
and over water.
0
Safety risks associated with bored tunnels - working in confined
space
-
Safety risks associated with bored tunnels - working in confined
space
-
Assess the relative safety during
Operations, maintenance and
decommissioning , and Emergency access
0
Safety risks associated with bored tunnels- operation and
maintenance in confined space
-
Safety risks associated with bored tunnels- operation and
maintenance in confined space
-
Commitments
Previous explicit or implicit public
assurances or commitments to third
parties
N/A
0
Possibility of increased programme duration - this would impact on
commitment to open HS2 in 2026. However avoids the need for
utilities diversions and relocation of businesses during construction
(HOAC)
0
Possibility of increased programme duration - this would impact on
commitment to open HS2 in 2026. However avoids the need for
utilities diversions and relocation of businesses during construction
(HOAC)
0
Commercial
Development
Does the option provide opportunities for
development in particular for over station
development
N/A
0
N/A
0
N/A
0
Overall Rating
0
Overall Rating
---
Overall Rating
---
Preferred Option:
Option A
Reason:
Cost, programme implications, construction safety, major traffic
movements for the removal of tunnel excavated material.
`Code
1 -
Accepted
Uncontrolled when printed
INTERNAL INFORMATION
Northern Extension of Northolt Tunnel SIFT Report
Northern Extension of Northolt Tunnel SIFT Report
C222-ATK-DS-REP-020-000034
Revision – P06
Page 44
Uncontrolled when printed
INTERNAL INFORMATION
9 Environmental Appraisal Template
Table 9.1 Northern Extension of Northolt Tunnel Environmental Appraisal SIFT Assessment Table
Location:
Colne Valley
OPTIONS CONSIDERED:
Option A
The Proposed Scheme as submitted in the hybrid Bill
(Northolt Tunnel to West Ruislip/ Viaduct across the Colne
Valley/ Chiltern tunnel east of M25 between jnc 16 and
17)
Option B
Above ground section between Northolt and Chiltern tunnels
placed underground in bored tunnels with provision for
connection spurs to Heathrow
Option C
As per option B but with no passive provision for a connection
to Heathrow
OPTION DESCRIPTION
Key Sustainability
Issue
Topic
STAGE:
Constructio
n or
Operation
EDA
Considered
(incl. Topic
and Ref no.)
Comment
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
Greenhouse gas
emissions and
climate change
Climate
adaptability
Const
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Op
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Greenhouse
gas
emissions
Const
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Op
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Energy use
Const
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Op
Not assessed
N/A
Not assessed
N/A
Not assessed
N/A
Natural and
cultural resource
protection and
environmental
enhancement
Landscape/
townscape
Const
LV3 and LV6
The viaduct and associated embankments, cuttings
and tunnel portals are not within any listed
landscape areas; however the intricate mosaic of
water features and woodland blocks of the Colne
Valley gives the area a distinctive landscape
characteristic and make up the bulk of the Colne
Valley Regional Park.
There are a large number of residential, recreational
and commercial receptors that may suffer visual
impact due to the viaduct construction, these
include (but are not limited to) residents of Denham,
Denham Green and South Harefield. Recreational
users of the Colne Valley lakes, local footpaths, the
River Colne and Grand Union Canal with associated
marina. Users and employees of the Hillingdon
Outdoor Activity Centre, local golf courses, Denham
Aerodrome, Denham Grove (De Vere Hotel) and
rail/road users.
1.1.1
There are two ancient
woodlands (Ranston Covert and
Battlesford Wood) which will be
directly impacted by the
o
Considerably reduced landscape and visual impact during
construction over the base case as the majority of this
option would be in tunnel.
Construction of the additional three vent shafts would
have a local impact on the landscape and visual character
of these areas.
The 700m long ‘gap’ structure, located close to the
Chiltern tunnel south portal and cutting of the base case,
would have a broadly similar direct impacts, although
considerably more excavated material would be handled
at this location as a consequence of the extension of the
Chiltern tunnel.
There may be localised adverse visual impacts caused by
the T3 vent shaft during construction.
1.1.2
There
would be reduced adverse
impact from there not being a
requirement for construction
activity relating to the National Grid
pylon diversion.
+++ As Option B. With the lack of the Heathrow Spur there
may be reduced impact from a lessor quantity of
excavated material being stockpiled within the main
compound.
+++