`Code
1 -
Accepted
Uncontrolled when printed
INTERNAL INFORMATION
Northern Extension of Northolt Tunnel SIFT Report
Northern Extension of Northolt Tunnel SIFT Report
C222-ATK-DS-REP-020-000034
Revision – P06
Page 49
Uncontrolled when printed
INTERNAL INFORMATION
Location:
Colne Valley
OPTIONS CONSIDERED:
Option A
The Proposed Scheme as submitted in the hybrid Bill
(Northolt Tunnel to West Ruislip/ Viaduct across the Colne
Valley/ Chiltern tunnel east of M25 between jnc 16 and
17)
Option B
Above ground section between Northolt and Chiltern tunnels
placed underground in bored tunnels with provision for
connection spurs to Heathrow
Option C
As per option B but with no passive provision for a connection
to Heathrow
OPTION DESCRIPTION
Key Sustainability
Issue
Topic
STAGE:
Constructio
n or
Operation
EDA
Considered
(incl. Topic
and Ref no.)
Comment
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
pochard for breeding, and habitat used by corn
bunting and coral root; effects that are assessed as
significant at the county/ metropolitan level.
1.1.6
Construction
The Scheme
through will pass through
habitats used by otter,
watervole, bats, breeding and
wintering birds, reptiles and
great crested newts, which
could result in significant
adverse effects at the county/
metropolitan level.
Op
No significant effects have been identified for the
operational phase.
o
The tunnel section passes under the majority of the
features listed in the base case and has no impact on
them.
Overall the operational impact of this option is
significantly reduced compared to Option A.
+++ As Option B.
+++
Water and
flood risk
Const
WR2, WR3,
WR4, WR6
Construction within the lakes has the potential to
generate impacts on water quality which could lead
to a risk of a significant adverse effect.
1.1.7
If ground fissures connect the working area of the
Proposed Scheme directly to very high value
groundwater receptors such as Public Water Supply,
the impact of even low levels of turbidity could
cause the closure of a source due to the high quality
required to be met for Public use. This risk is
especially the case where the Colne Valley viaduct
piers are sited within the areas designated SPZ1
TH177 and SPZ1 TH174 and where the SPZ1 TH027
will be intercepted by the retaining walls for the
Tilehouse Lane cutting. If a PWS was forced to shut
down this would be a major impact and will
o
The tunnel section passes under the majority of the
surface water features listed
in the base case and has no
impact on them.
The majority of the tunnel from Ch 023+750 northwards
passes through SPZ1, with two small sections in SPZ2.
These are at Wyatt’s Covert Caravan Site and a section
from the Hillingdon Outdoor Activity Centre to the Harvil
Road.
Construction of the tunnel and cavern to accommodate
the Heathrow spur turnouts below the water table and in
SPZ1/2 has the potential to alter the risks to groundwater
flows and licensed abstractions providing key potable
water supplies. Although the programme of works in
SPZ1 is longer than Option A, the work would be focussed
in one or two areas at a time and the risks in those areas
--
As Option B. However, avoidance of large caverns for
the turnouts reduces potential
impacts upon
groundwater compared to Option B.
--
`Code
1 -
Accepted
Uncontrolled when printed
INTERNAL INFORMATION
Northern Extension of Northolt Tunnel SIFT Report
Northern Extension of Northolt Tunnel SIFT Report
C222-ATK-DS-REP-020-000034
Revision – P06
Page 50
Uncontrolled when printed
INTERNAL INFORMATION
Location:
Colne Valley
OPTIONS CONSIDERED:
Option A
The Proposed Scheme as submitted in the hybrid Bill
(Northolt Tunnel to West Ruislip/ Viaduct across the Colne
Valley/ Chiltern tunnel east of M25 between jnc 16 and
17)
Option B
Above ground section between Northolt and Chiltern tunnels
placed underground in bored tunnels with provision for
connection spurs to Heathrow
Option C
As per option B but with no passive provision for a connection
to Heathrow
OPTION DESCRIPTION
Key Sustainability
Issue
Topic
STAGE:
Constructio
n or
Operation
EDA
Considered
(incl. Topic
and Ref no.)
Comment
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
therefore result in a significant adverse effect.
1.1.8
The jetty used during the viaduct construction has
the potential to obstruct some flood flows
temporarily during the construction works resulting
in moderate impacts on flood risk to very high value
receptors with a resulting large and significant
adverse effect.
better defined and this may reduce the need for
simultaneous closure of groundwater sources. The
tunnels’ vertical alignment would avoid the need for
multiple holes penetrating through the shallow aquifer
into the deep aquifer. A deeper alignment may be
preferred if it avoids the main intake sections of the water
supply boreholes, though any change would be limited
due to rail gradient requirements.
Groundwater mitigation measures would still be required
although the maximum flow requirement may be
reduced.
Groundwater quality in the vicinity of Shaft “E2” may be
affected by contamination from New Years Green Landfill
although the draft CoCP measures would address this.
The tunnel would occlude more of the effective aquifer
than the proposed, Option A pile groups. Potential extra
drawdown and loss of peak output of up to 40% could
occur at Potable Water Supply source. A new water
supply borehole immediately south west of the tunnels
could be a suitable mitigation measure. A deeper
alignment may be preferred if it then avoids the main
fissures and intake sections of the water supply
boreholes.
The flood risk to temporary works would be less than
Option A since there are fewer above ground works in the
flood plain
Op
With careful management of viaduct drainage into
the surface water bodies, no operational impacts
have been identified.
o
The need for viaduct drainage passing directly into surface
water bodies would avoided. No operational impacts have
been identified.
o
No operational impacts have been identified.
o
Creating
sustainable
communities
Air quality
Const
There will be substantial adverse impacts along
Swakeleys Road, between Harvil Road and the A40,
at a number of receptors assessed for NO2 as a
consequence of construction traffic which are
significant.
o
Air quality as a consequence of an increase in highway
construction traffic associated with the removal of surplus
excavated material from site could be severely affected.
A detailed assessment would need to be undertaken in
order to fully assess the implications of the additional
construction traffic on air quality.
--
As Option B.
--