`Code
1 -
Accepted
Uncontrolled when printed
INTERNAL INFORMATION
Northern Extension of Northolt Tunnel SIFT Report
Northern Extension of Northolt Tunnel SIFT Report
C222-ATK-DS-REP-020-000034
Revision – P06
Page 54
Uncontrolled when printed
INTERNAL INFORMATION
Location:
Colne Valley
OPTIONS CONSIDERED:
Option A
The Proposed Scheme as submitted in the hybrid Bill
(Northolt Tunnel to West Ruislip/ Viaduct across the Colne
Valley/ Chiltern tunnel east of M25 between jnc 16 and
17)
Option B
Above ground section between Northolt and Chiltern tunnels
placed underground in bored tunnels with provision for
connection spurs to Heathrow
Option C
As per option B but with no passive provision for a connection
to Heathrow
OPTION DESCRIPTION
Key Sustainability
Issue
Topic
STAGE:
Constructio
n or
Operation
EDA
Considered
(incl. Topic
and Ref no.)
Comment
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
QUALITATIVE IMPACT DESCRIPTION
and/or QUANTITIVE ASSESSMENT
RATI
NG
1.1.11
Overall, the temporary construction impact on BMV
agricultural land by Option B and C would be comparable
to the Proposed Scheme. The three holdings affected
would still experience comparable impacts to those
identified for the Proposed Scheme.
Once the land is restored to agriculture (if that is the
intended end result) the permanent impact on
agricultural land and the three land holdings would
reduce.
There would be minimal temporary or permanent impacts
on forestry, and negligible impacts to the soil resource.
Op
No operational impacts.
o
No operational impacts.
o
As Option B.
o
Land quality
Const
No construction impacts.
o
No construction impacts.
o
As Option B.
o
Op
No operational impacts.
o
No operational impacts.
o
As Option B.
o
Waste &
material
resources
Const
This option does not generate significant excavated
material as the alignment is on viaduct or at or near
grade. Sustainable placement areas are located
within the Colne Valley area to accommodate
surplus excavated from excavations.
1.1.12
1.1.13
o
The scale of below ground works associated with Option B
would result in the generation of a large quantity of
excavated material. Since the tunnel also removes the
need for engineering fill material and mitigation
earthworks, this would substantially increase the total
volume of excavated material generated. The volume of
surplus excavated material needing to be disposed would
increase to 4.22 million cubic meters
This assessment does not include any provision for
additional local sustainable placement of site.
---
As Option B, although the volumes would be
slightly less
as there would be no requirement to create the caverns
to accommodate the turnouts for the Heathrow Spur.
---
Op
Not assessed at this stage
N/A
Not assessed at this stage
N/A
Not assessed at this stage
N/A
Overall Rating
Significant above ground construction and
operational impacts have been identified for this
option including; noise, visual and ecological
impacts. The options will result in a number of utility
diversions. Material derived from the Chiltern tunnel
would be used to mitigate operational noise and
landscape impacts, which would allow the vast
majority of excavated material to remain on site.
o
This option would avoid the majority of the above ground
impacts identified in Option A during construction and
operation including indirect impacts as a consequence of
utility diversions. The additional tunnelling will generate
significant volumes of additional spoil. Spoil from the
Chiltern tunnel that was to be used for on-site mitigation
in Option A would no longer be retained on site as the
requirement for mitigation would be removed in Option
+++
As Option B, although there would be a slight reduction
in spoil generated and removed from site that would
also slightly reduce construction traffic numbers
compared to Option B. From an environmental
perspective this option is considered the preferred
option. However, further detailed assessment work of
the implications for off-site disposal would need to be
undertaken and options to reduce the volume of
+++