Proposal for Northern Extension of Northolt Tunnel sift report



Yüklə 0,76 Mb.
Pdf görüntüsü
səhifə19/27
tarix18.05.2018
ölçüsü0,76 Mb.
#44521
1   ...   15   16   17   18   19   20   21   22   ...   27

`Code 

1 - 


Accepted

Uncontrolled when printed 

INTERNAL INFORMATION

 

Northern Extension of Northolt Tunnel SIFT Report 



 

 

Northern Extension of Northolt Tunnel SIFT 



Report C222-ATK-DS-REP-020-000034 

Revision – P06 

 

                      41 



Uncontrolled when printed 

 

 



7.5.7 

Tunnelling has previously been undertaken in a SPZ1 area (National Grid Croydon Cable 

Tunnel, London), where contamination was carefully avoided through an extensive pre-

construction  groundwater  monitoring,  sampling  and  testing  programme  which  was 

developed through consultation with the Environment Agency. 

7.5.8 


The  relocation  of  the  HOAC  (Hillingdon  Outdoor  Activity  Centre)  site  would  not  be 

required under Options B and C. 

 

 

 



 

 



`Code 

1 - 


Accepted

Uncontrolled when printed 

INTERNAL INFORMATION 

Northern Extension of Northolt Tunnel SIFT Report  

 

 

Northern Extension of Northolt Tunnel SIFT Report  



C222-ATK-DS-REP-020-000034  

Revision – P06 

 

                         



                                            Page 42                                                

 

                                                                                       Uncontrolled when printed 



 

INTERNAL INFORMATION 

 

8 Evaluation against Assessment Criteria 

Table 8.1 Northern Extension of Northolt Tunnel Engineering Appraisal SIFT Assessment Table 

Location: 

Colne Valley 

Option name and description: 

Community Forum Request for Northolt Tunnel Extension 

 

OPTIONS CONSIDERED: 







OPTION DESCRIPTION 

Proposed Scheme 

Tunnel with Heathrow Spur Provision 

Tunnel without Heathrow Spur Provision 

Headings 

Appraisal criteria 

QUALITATIVE IMPACT ASSESSMENT 

and/or QUANTITIVE ASSESSMENT 

RATIN

G

 

QUALITATIVE IMPACT ASSESSMENT 

and/or QUANTITIVE ASSESSMENT 

RATIN

G

 

QUALITATIVE IMPACT ASSESSMENT 

and/or QUANTITIVE ASSESSMENT 

RATIN

G

 

Strategic Fit 

Capture whether an option meets the 

Project Specification 

The solution is in accordance with the project 

specification and technical requirements. 

The solution is in accordance with the project specification and 



technical requirements. 

0

 



The solution is in accordance with the project specification and 

technical requirements. 

0

 

Construction 



Feasibility 

Assess the relative complexity of 

construction 

Assess the relative construction 

programme  

Viaduct construction is standard, aligns with rest of 

adjacent sections of viaduct construction and allows 

repeated use of formwork and temporary works.  

 

There is a localised diversion of the River Colne to ensure 



that none of the viaduct piers are located within the river. 

This may require temporary works in order to construct 

the piers adjacent to the river bank. 

 

 



The  8.8m  internal  diameter  main  tunnels  will  be  constructed  by 

TBM  as  previously  proposed  for  the  Northolt  and  Chiltern  tunnels. 

The passive provision for the Heathrow spur requires that significant 

sized caverns are constructed of spans in excess of 20m. 

 

A tapered gap structure with maximum width of 70m, depth of 20m 



and 700m long box structure will be required with connecting access 

tracks which will allow passenger evacuation. 

 

Three additional intervention and ventilation shafts will be required 



at nominally 3000m intervals. 

 

Requires relocation of ATFS compared to Option A. 



 

Construction  period  for  the  Northolt  tunnel  extension  associated 

with  Options  B  and  C  is  19  months  assuming  2  No.  TBMs  which 

would  run  in  parallel  with  Chiltern  and  Northolt  tunnel 

constructions. 

 

Extension  of  construction  time  for  Chiltern  tunnel  (1  month), 



Northolt  tunnel  (2  months)  or  Rail  Systems  (3  Months)  may  affect 

overall programme time. 

The  8.8m  internal  diameter  main  tunnels  will  be  constructed  by 



TBM as previously proposed for the Northolt and Chiltern tunnels.  

 

A tapered gap structure with maximum width of 70m, depth of 20m 



and 700m long box structure will be required with connecting access 

tracks which will allow passenger evacuation. 

 

Three additional intervention and ventilation shafts will be required 



at nominally 3000m intervals. 

 

Requires relocation of ATFS compared to Option A. 



 

Construction  period  for  the  Northolt  tunnel  extension  associated 

with  Options  B  and  C  is  19  months  assuming  2  No.  TBMs  which 

would  run  in  parallel  with  Chiltern  and  Northolt  tunnel 

constructions. 

 

Extension of construction time for Chiltern tunnel (1 month), 



Northolt tunnel (2 months) or Rail Systems (3 Months) may affect 

overall programme time. 

Assess the relative disruption to existing 



infrastructure, e.g. rail, highways etc. 

N/A 


Additional burden on public roads for servicing tunnel construction. 

 

Removal of excavated material from the construction compound by 



the M25 would significantly increase the lorry movements within 

the M25 and local roads. 

 

Diversion of Harvil Road. 



- - 

Additional burden on public roads for servicing tunnel construction.  

 

Removal of excavated material from the construction compound by 



the M25 would significantly increase the lorry movements within 

the M25 and local roads. 

 

Diversion of Harvil Road. 



- - 

HS2 Operation 

Feasibility – Trains 

(HS2 and Network 

Rail) 

Assess the relative flexibility and 



reliability of the track layout 

Assess the relative train maintenance and 

servicing arrangements 

Maintenance required on viaduct. 

Maintenance required through tunnel. 



Maintenance required through tunnel  

HS2 Operation 



Feasibility –Operations 

(Stations, Depots etc.) 

Assess the effectiveness of 

Location and space for station control 

Location and space for accommodating 

staff, catering, transport police and other 

“back of house” activities 

N/A 


Required to assess the fire life safety strategy for the cases where 

caverns present, especially at turnout T2. 

Required to assess the fire life safety strategy for the cases where 



caverns present. 




Yüklə 0,76 Mb.

Dostları ilə paylaş:
1   ...   15   16   17   18   19   20   21   22   ...   27




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə