53
•
continuous
communications and analysis, and
•
annual evaluation.
6.2.2.4
Annual Workshops
Annual workshops among COP staff are needed to plan strategy for each T&O season.
The T&O situation is different each year, so the T&O strategy must be adaptive.
Some key topics that need to be addressed in these workshops include:
1. Hydrologic forecast. The hydrologic forecast is important for planning blending and
source switching options. SRP and CAWCD plan by March based on the
hydrologic situation for the upcoming year.
2. Water delivery situation. This issue depends upon both the hydrologic forecast and
various institutional and infrastructure issues. For example,
the potential for source
switching depends not only upon the hydrologic situation, but also upon the
availability of excess treatment capacity. The amount of excess treatment capacity
will vary from year-to-year. Legal and institutional issues also constrain the extent
of blending that will be possible in a given year.
3. Other infrastructure issues. The status of PAC delivery systems, the status of plant
maintenance,
canal shutdowns, and other issues affect the development of the
season’s T&O management strategy.
4. Program evaluation. It is critical that the T&O program be evaluated at the end of
each season. The program evaluation should result in a concise list of ideas to
improve T&O management for the following year.
54
SECTION 7
CASE STUDIES
7.1 INTRODUCTION
The principles developed in this Manual are illustrated using three case studies. These
are actual events that were encountered during the T&O study. They were selected to
illustrate possible management practices that might be employed in response to T&O
problems at the upper end of the water supply system, in the canal system, and at the
water treatment plants. Specifically, the case studies are:
•
high MIB in Saguaro Lake during late summer, 2001
•
high MIB in a "hot spot" along Arizona Canal during July, 2001
•
high MIB in the influent to the Squaw Peak WTP
7.2 CASE STUDY #1 - HIGH MIB IN SAGUARO LAKE
7.2.1 Process Control Monitoring
MIB concentrations had been higher than geosmin levels during the summer of 2001 in
Saguaro Lake. By the end of August 2001 MIB concentrations in the epilimnion of
Saguaro Lake had reached 47 ng/L. The following data were collected during sampling
in Saguaro Lake (August 30, 2001):
Depth from
surface (m)
MIB
(ng/L)
Geosmin
(ng/L)
Temperature
(
o
C)
Dissolved Oxygen
(mg/L)
0
47
7
28.0
7
5
36
7
25.8
4
10
19
5
24.3
2
15
16
6
23.8
2
20
12
4
23.5
2
25
12
4
23.4
2
30
5
4
22.9
2
7.2.2 Diagnosis
Water leaving Saguaro Lake via the hypolimnion withdraw was at approximately 30 m
depth. Therefore MIB concentrations were low, but significant MIB accumulated in the
lake and would soon reach the withdrawal depth. The reservoir had weak thermal
stratification (
∆
Temp
max
= 28.0 – 22.9 = 5.1
o
C) but still exhibited a strong dissolved
oxygen stratification. Water above 5 m had oxygen concentrations > 4 mg/L and water
55
at and below 10 m had oxygen concentrations of ~ 2 mg/L. It was concluded that the
reservoir would probably destratify within 30-45 days, resulting in higher MIB
concentrations throughout the water column as the water became completely mixed.
The result would be a significant increase in MIB concentration in the water leaving the
reservoir from approximately 5 ng/L to > 15 ng/L.
7.2.3 Treatment Selection
Logistical, economic and political considerations prevented chemical or biological
treatment for MIB in Saguaro Lake. Therefore, it was decided that three implementation
strategies should be undertaken to minimize MIB concentrations at downstream
locations.
First, SRP was contacted to determine the feasibility of switching from the Salt River to
the Verde River as the dominant water source earlier than usual. This switch in water
supplies generally occurs in mid-October to mid-November. Bartlett lake on the Verde
River had much lower MIB concentrations (< 15 ng/L in the epilimnion and < 5 ng/L in
the hypolimnion). SRP determined that the Verde River did not have sufficient water
volume to make the switch in water supplies earlier than scheduled. This option was
therefore not implemented.
Second, CAP and SRP were contacted to determine if more CAP water could be
delivered into the Arizona Canal and less SRP water (i.e., Salt River water). The CAP
canal had low MIB levels (< 5 ng/L) as did Lake Pleasant (< 15 ng/L). It was
determined that for approximately two weeks in late September or early October a
larger delivery of low-MIB CAP water could be delivered into the Arizona Canal. This
would dilute MIB concentrations originating from Saguaro Lake via the Salt River. This
option was implemented.
Third, City of Phoenix water production staff were contacted to evaluate the potential to
increase finished water production at the Union Hills WTP rather than WTPs on the
Arizona Canal. MIB levels in the CAP canal would be significantly lower than MIB levels
in the Salt River that supplies the major flow in the Arizona Canal. It was decided to
keep Deer Valley WTP off-line, minimize production at Squaw Peak WTP and increase
production at Union Hills WTP. This option was implemented.
7.2.4 Treatment Application
Increased CAP flows into the head of the Arizona Canal were implemented and
production shifted from WTPs on the Arizona Canal to the CAP canal.
7.2.5 Follow-up Monitoring
Continued monitoring of Saguaro Lake proved that the MIB concentrations in the
epilimnion continued to increase after August 30, 2001 as “predicted” (see Figure 7-1).
MIB concentrations leaving Bartlett Lake on the Verde River never exceeded 10 ng/L