this RFT.
5.
; (SWTC Appendix 40)
The Tenderer must provide the information identified in Appendix 3, Table 5 of
this RFT.
6.
Initial Earthworks Plan; (SWTC Appendix 42)
The Tenderer must provide the information identified in Appendix 3, Table 6 of
this RFT.
7.
Training and Apprenticeship;
The Tenderer must demonstrate its commitment and capacity to plan and
manage training in accordance with the NSW Government Procurement
Guideline
Skills and Training in the Construction Industry.
The Tenderer must provide the skills and training development
details identified
in Appendix 3, Table 9 of this RFT, (i.e. “Schedule of Skills Development and
Training”).
8.
Workplace Relations Management Plan (State); (SWTC Appendix 45)
The Tenderer must provide the information identified in section 6.1, Obligations
in Expressions of Interest or tender response, of the New South Wales
Government's Implementation Guidelines to the New South
Wales Code of
Practice for Procurement: Building and Construction.
9.
Workplace Relations Management Plan (Commonwealth); (SWTC
Appendix 44)
The Tenderer must provide the information identified in Part 6 of the Building
Code.
10.
Initial Work Health and Safety Management Plan; (SWTC Appendix 41)
The Tenderer must provide the information identified in Appendix 3, Table 7 of
this RFT.
11.
Initial Chain of Responsibility (CoR) Management Plan; (SWTC Appendix
39)
The Tenderer must provide the information identified in Appendix 3, Table 8 of
this RFT.
If successful, the Contractor will be required to provide a monthly report on how
the Contractor is meeting
compliance with the chain of responsibility provisions of the
Heavy Vehicle Law
.
12.
Aboriginal Participation
The Tenderer must demonstrate its commitment and capacity to plan and
facilitate Aboriginal participation
in employment, training and development of
Aboriginal enterprises in accordance with the NSW Government
Policy on
Aboriginal Participation in Construction
.
The Tenderer must provide in its Tender:
a) evidence of its ability to meet the obligations under the Policy on the
Contract;
b) details of its Aboriginal participation in construction performance outcomes
on other RMS or NSW Government contracts;
c) an undertaking that, in the event that it becomes the Contractor, it is prepared
to provide an Aboriginal Participation Plan and the Aboriginal Participation
Reports, which
must comply with the Policy; and
IC-DC-C92
D&C Request for Tender
Edition 1, Revision 21, September 2017
Page 23
d) proposed exclusions for determining the TPS (as defined in clause 4.10.3(c)
of this RFT).
(iii)
The Tenderer must identify the elements of the design (design lots) that the Tenderer
proposes to be covered by item 25A of Schedule 1 of the Project Deed.
(g)
Volume V: Project Cost (Excluding Project Verifier and Environmental Representative)
(i)
The Contractor's Work is to be divided into a number of Cost Centres allocated to the
following schedules to the Project Deed:
A.
Design Payment Schedule; and
B.
Construction Payment Schedule.
(ii)
Each of these Cost Centres represents a major item or series of interrelated items associated
with the Contractor's Work.
(iii)
The Cost Centres are subdivided into a series of Milestones. Payment for the Contractor’s
Work will be made against progressive achievement of each Milestone in accordance with
clause 18 of the Project Deed.
(iv)
Any Service Work not included in Schedule 2, Milestone 5 or Schedule 3, Cost Centre 9 as
Provisional Sum Works must be allowed for elsewhere in the
either the Design Payment
Schedule or the Construction Payment Schedule.
(v)
In respect of the Contractor’s Work the Cost Centres and Milestones currently included in
the Project Deed are based upon RMS’ assumptions as to methods of construction and
program for the Project Works, Landscaping Maintenance and Temporary Works. The
Tenderer must break down the milestones in the Design Payment Schedule to reflect the
Tenderer’s proposed method for development of the Design Documentation and to provide
payment information for the design elements within the milestone.
(vi)
In the event that the proposed methods of construction or program differ significantly from
the assumptions inherent in the content of Cost Centres, the selection and description of
Milestones and/or the periods for the
achievement of Milestones, the Tenderer may
propose alternative descriptions of the Cost Centres and Milestones, and/or alternative
periods for their achievement (except for the Milestones that identify the noise attenuation
works). The Tenderer must include with its Tender an explanation of, and the reasons for,
any such changes. The principles to be followed must reflect the approach taken in the
payment schedules as listed below.
(vii)
The precise description of the work to be achieved in the Cost Centres
and Milestones must
be submitted with the Tender having regard to the Tenderer's proposed methods and
programs for performing the Contractor's Work and be in sufficient detail to accurately
determine and check the quantum of progressive payments claimed under the provisions of
clause 18.2 of the Project Deed. The Tenderer must submit the following details:
A.
Payment Schedules
1.
Design Payment Schedule including payment constraint information,
excluding the amounts for:
•
Project Verifier’s design verification services including Project
Verifier’s fees and Contractor’s margin and contingency – (Schedule
2, Milestone
[insert number] to the Project Deed); and
•
Environmental Representative's design phase services including
Environmental Representative's fees and Contractor’s
margin and
contingency – (Schedule 2, Milestone
[insert number] to the Project
Deed).
2.
Construction Payment Schedule including a comprehensive breakdown
and details on the noise attenuation works, excluding the amounts for:
IC-DC-C92
D&C Request for Tender
Edition 1, Revision 21, September 2017
Page 24