TA 8119 NAMA Report_FINAL_Appendix 5 NAMA Registry Submission Form _ AZE Renewable Energy
(iii) By 2015, preparation of proposals to the government on preferential loans for renewable
energy;
(iv) Preparation of tariff proposals for alternative and renewable energy sources by 2016;
(v) Analyze specific processes in agricultural and food production that can benefit from renew-
able energy and prepare suggestions for realizing the identified
benefits within the Samukh
Complex and replicating these at other sites; and
(vi) Complete feasibility studies for establishing similar agro-renewable energy complexes at
sites in Nakhchivan, Gadabav, Neftchala, Balakan, and Oghuz.
Phase 2 (2017-2020) will expand the Samukh Complex and begin to use the lessons learned for repli-
cation at other sites in Azerbaijan.
A.4 Sector
Energy supply
Transport and its Infrastructure
Residential and Commercial buildings
Industry
Agriculture
Forestry
Waste management
Other
A.5 Technology
Bioenergy
Cleaner Fuels
Energy Efficiency
Geothermal energy
Hydropower
Solar energy
Wind energy
Ocean energy
Carbon Capture and Storage
Low till / No till
Land fill gas collection
Other
A.6 Type of
action
National/ Sectoral goal
Strategy
National/Sectoral policy or program
Project: Investment in machinery
Project: Investment in infrastructure
Project: Other
Other: Includes a pilot project based on renewable energy at an
agro-energy
complex, which will then be replicated at 5 other sites in Azerbaijan.
A.7 Greenhouse gases covered by the action
CO
2
CH
4
N
2
O
HFCs
PFCs
SF
6
Other
B National Implementing Entity
B.1.0 Name
Azerbaijan State Agency of Alternative and Renewable Energy Sources
B.1.1 Address
40 Uzeyir Hajibeyov Street, Government House, Gate IV, Baku,
Azerbaijan
Republic, AZ1000
TA 8119 NAMA Report_FINAL_Appendix 5 NAMA Registry Submission Form _ AZE Renewable Energy
B.1.2 Contact Person
Jamil Malikov
Alternative Contact Person
B.1.3 Phone
(+99412) 493 72 75
Alternative Phone
B.1.4 Email
info@area.gov.az
Alternative Email
+ Add Additional entity
C. Expected timeframe for the implementation of the mitigation action
C.1 Number of years for completion
7 years
C.2 Expected start year of implementation
2014
D.1 Used
Currency
USD
Conversion to USD
E Cost
E.1.1 Estimated full cost of implementation
277,900,000
Conversion to USD
E.1.2 Comments on full cost of implementation
Table 1 shows the likely sources of financial support for Phases 1 and Phase 2 of the NAMA. The cost
estimate includes feasibility studies for the Samukh Complex and five other sites, construction and
technical assistance for implementation of Samukh, and work on the normative and regulatory
framework for renewables.
Proposed Budget and Requested Financing
Activity
Million $
(exchange rate as of May 15, 2015)
Phase 1
Phase 2
Total
Total implementation cost
Renewable energy capacity at Samukh
Feasibility studies, technical assistance, etc.
55.2
44.0
11.2
222.7
167.7
55.0
277.9
211.7
66.2
Total amount covered by state budget
NAMA implementation
Feasibility studies
12.9
11.0
1.9
44.5
44.5
TBD
57.4
55.5
1.9
Total amount from private sector
11.0
44.5
55.5
Total amount of support requested
31.3
133.7
165.0
Renewable energy capacity
Technology transfer support
TBD
TBD
TBD
TBD
TBD
TBD
TA 8119 NAMA Report_FINAL_Appendix 5 NAMA Registry Submission Form _ AZE Renewable Energy
Technical assistance:
financial management system
Technical assistance: business management
Technical assistance: evaluation of lessons learned for replication
Technical assistance: revision to legal and regulatory norms
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
E.2.1 Estimated incremental cost of implementation
0.00
Conversion to USD
E.2.2 Comments on estimated incremental cost of implementation
F Support required for the implementation of the mitigation action
F.1.1 Amount of financial support
165,000,000
Conversion to USD
F.1.2 Type of required financial support
Grant
Carbon finance
Loan (sovereign)
Other
Loan (Private)
Concessional loan
Guarantee
Equity
F.1.3 Comments on Financial Support
F.2.1 Amount of Technological Support
0.00
Conversion to USD
F.2.2 Comments on Technological Support
F.3.1 Amount of capacity building support
0.00
$ (Dollars)
Conversion to USD
F.3.2Type of required capacity building support
Individual level
Institutional level
Systemic level
Other
F.3.3 Comments on Capacity Building Support
F.4 Financial support for implementation required
F.5 Technological support for implementation required
F.6 Capacity building support for implementation required
G Estimated emission reductions