Contractor finds any discrepancy in the Drawings or between
the Drawings, Specifications and Schedule of Quantities he
shall immediately refer the same in writing to the
Architect,
who shall decide which shall be followed, and his decision
shall be final and binding on all parties. The Contractor shall
provide ground for himself and fresh water and power for
carrying out of the works at his own cost.
b) The
Bank shall not charge the Contractor for his own un -
rented ground but shall on no account be responsible for the
expenses incurred by the Contractor for hired ground.
c) The Contractor shall provide and maintain all measuring and
testing instruments at all times for properly carrying out the
work and for the use of the
Architect / Bank, including
providing skilled attendants as required.
d) The Contractor shall supply, fix and maintain at his cost
during the execution of any works, all the necessary
equipment, materials and lighting required by night and as
well as by day for proper execution of work. The contractor
shall take down and remove any or all such unwanted waste
materials, debris etc. as occasion shall require or when
ordered to do so, and shall fully reinstate and make good all
matters and things described during the execution of the
works, to the satisfaction of the
Architect / Bank
8.1.8.
FACILITIES TO OTHER CONTRACTORS
a) The Contractor shall give full facilities and co-operation to
other Contractors employed by the
Bank and shall afford
them reasonable opportunity for the execution of their works
and for properly connecting and co-coordinating their works
with the work of the other Contractors. The decision of the
Architect on any points of dispute between the various
Contractors shall be final and binding on all parties
concerned.
8.1.9.
STORES AT SITE:
a) The Contractor shall be allotted space / existing rooms on
site subject to availability. The Contractor shall make his own
arrangements to enclose, secure and guard the space
allotted to him. Wherever there may be materials, which are
likely to deteriorate by the action of the sun, rain or other
elements, all such materials, tools etc shall be duly protected
by the Tenderer from damage by weather or any other
cause. All such stores and yards shall be cleared away and
ground left in good and proper order, on completion of this
Contract unless otherwise expressly mentioned herein.
8.1.10.
ELECTRIC POWER FOR INSTALLATION
a) The Contractor shall be given a temporary electrical
connection at one location at or below ground level to be
SAILESH NAIR & ASSOCIATES
- 52 -
BOB, ANKALAV BRANCH, DIST. ANAND
1, DEFENCE KARMACHARI HSG. SOC. NR. UNITED COLONY, B/H. NAVRACHANA HIGH SCHOOL, SAMA,
VADODARA – 390 008 TELE-FAX. 0265 2784382 MOB : 9898072813 / 9427602817
decided by the
Bank. The Contractor shall, at his own cost,
provide a sub-meter, cabling and wiring and switchboards
complying with all laws, rules and regulations in force and
ensuring the safety of everyone working or visiting on site.
b) The Contractor shall regularly reimburse cost for electricity
consumed to the Main Contractor at the same tariff rates as
charged by the Electric Supply Company.
8.1.11.
GENERAL CONDITIONS OF SUPPLY OF MATERIALS
FOR EXECUTING INTERIOR FLOORING WORK
The successful Tenderer before placing the orders or before
supplying shall seek clearance in a meeting with the
Bank /
Architect. The final list of supply of materials shall however
be made at the time of signing of the contract by the
Bank in
consultation with the
Architect and the successful Tenderer.
The Contractor shall then strictly adhere to these approved
lists of makes and materials and proceed to supply the
same. If any deviation and/or for any unforeseen reasons the
makes or materials are to be altered, the contractor shall
obtain the approval from the
Bank / Architect in writing and
then only he may proceed to supply.
8.1.12.
REMOVAL OF ALL OFFENSIVE MATTERS :
a) All soil, filth or other matter of an offensive nature taken out
of any trench, sewer, drain or other place shall not be
deposited on the surface, but shall be at once carried away
by the Contractor and disposed off as per the rules and
regulations of the Local Authorities concerned.
8.1.13.
UNFIXED MATERIALS:
a) When any materials intended for the works shall have been
placed at site by the Contractor, such materials shall not be
removed there from (except for the purpose of being used on
the works) without the written authority of the
Architect and
when the Contractor shall have received payment in respect
of any Certificate in which the
Architect shall have stated
that he has taken into account the value of such unfixed
materials on the works, such materials shall become the
property of the
Bank, and the Contractor shall be liable for
any loss or damage to any such materials.
8.1.14.
REMOVAL OF IMPROPER WORK AND MATERIALS:
a) The
Architect shall, during the progress of the works, have
power to order in writing from time to time the removal from
the works, within such reasonable time as may be specified
in the order, of any materials which, in the opinion of the
Architect are not in accordance with the specifications or the
instructions of the
Architect and the substitution of proper
materials and the removal and proper re-execution of any
work, which has been executed with materials or