workmanship, not in accordance with the Drawings and
Specifications or instructions, and the Contractor shall
forthwith carry out such order at his own cost. In case of
default on the part of the Contractor to carry out such order
the
Bank shall have power to employ and pay other persons
to carry out the same and all expenses consequent there on
or incidental thereto shall be borne by the Contractor, and
shall be recoverable from him on behalf of the
Bank or may
be deducted by the
Architect'>Architect from any money due or that
may become due to the Contractor.
b) If the correcting works are not done in accordance with the
Contract the
Architect, in consultation with the
Bank, may
allow such work to be got done through other parties at
Contractors risk and cost and in that case they may make
allowance for the difference in value together with such
further allowance for damages to the
Bank as in their opinion
may be reasonable.
8.1.15.
CLEARING THE SITE OF WORKS:
a) The Contractor shall clear site of works as per the
instructions of the
Architect. The site of works shall be
cleared of all men, materials, sheds, etc. belonging to the
Contractor. The site shall be delivered in a clean and neat
condition as required by the
Architect within a period of one
week after the job is completed. In case of failure by the
Contractor, the
Bank under advice of the Architect will have
the right to get the site cleared at the risk and cost of the
Contractor to the satisfaction of the
Architect.
8.1.16.
OCCUPATION OF PARTIALLY COMPLETED WORKS BY
THE BANK:
a) The
Bank shall be entitled to and at liberty to occupy even
the partially completed works or any portion thereof by
themselves or through their agents and servants if they so
desire, in which event, necessary extension of time on this
account for completing the works shall however be granted
to the Contractor, but he shall have no claim for any
compensation whatsoever due to the delay involved in
completing works. Both the
Bank and the Contractor will
work out the repercussions on the insurance Clause
mentioned afore to mutual satisfaction safeguarding each
other’s interest.
8.1.17.
PREPARATION FOR OCCUPATION AND USE ON
COMPLETION:
a) On completion of the work, the Contractor shall inform the
Architect in writing that he has finished the work and it is
ready for the
Architect’s /
Bank’s inspection. The Contractor
shall clean all his works and all the rooms under his charge.
SAILESH NAIR & ASSOCIATES
- 54 -
BOB, ANKALAV BRANCH, DIST. ANAND
1, DEFENCE KARMACHARI HSG. SOC. NR. UNITED COLONY, B/H. NAVRACHANA HIGH SCHOOL, SAMA,
VADODARA – 390 008 TELE-FAX. 0265 2784382 MOB : 9898072813 / 9427602817
He will leave the entire works neat and clean and ready for
occupation and to the satisfaction of the
Architect.
8.1.18.
KEEPING THE AREAS AND ACCESS ROADS CLEAN:
a) The Contractor shall be required to maintain the site and the
building areas in a neat and clean condition at all times to the
satisfaction of the
Architect. Debris to be removed every 2
days.
b) The Contractor shall also be required to keep all access
roads to the site and within the site free from all obstructions,
material droppings etc. to the satisfaction of the
Architect
and local authorities.
8.1.19.
COVERING UP OF WORKS:
a) The Contractor shall cover up and protect the works from the
weather and shall suspend all wet operations during weather
which, in the opinion of
Architect, will be detrimental to the
works.
8.1.20.
MEASUREMENT TO BE RECORDED BEFORE WORK IS
COVERED UP:
a) The Contractor shall take joint measurements with the
Architect before covering up or otherwise placing beyond
the reach of measurement any items of work. Should the
Contractor neglect to do so, the same shall be uncovered at
the Contractor’s expense or in default thereof, no payment or
allowance shall be made for such work or the materials with
which the same was executed.
8.1.21.
SITE SURVEY:
a) On award of the works, the Contractor shall immediately
survey the complete site and record his findings on civil
works and services connected with his works and submit the
report in duplicate. No extra payment shall be made for this
work.
8.1.22.
LABOUR HUTMENTS:
a) The Contractor shall not be allowed to put up any hutment /
temporary structure of accommodating his labour/staff. He
shall be required to make these arrangements elsewhere at
his own cost. However, if the rules of local authorities so
permit and subject to the contractor arranging for such
permission, some space at site which will not come in the
way of the permanent construction, temporary construction
facilities and offices may be provided to the contractor at the
discretion of the
Bank for essential/core staff engaged on
emergency or essential services round the clock work with
proper sanitary facilities.
8.2.
STAFF MANAGEMENT