FINAL REPORT: DEFINITIONAL MISSION TO AZERBAIJAN: 
AZERCOSMOS – AZERSPACE-2 FEASIBILITY STUDY 
August 07, 2013 
Space Partnership International 
62 
 
and  (iii)  project  regulatory  risks,  i.e.,  risks  that  arise  from  the  regulatory  or  legal  factors 
governing access to the orbital spectrum and rights to offer services in countries within the satellites’ 
designated footprints. 
Task  9  Deliverable:   
The  Contractor  shall  prepare  a  risk  assessment  and  risk  mitigation report  based  on  the  selected 
design,  technical  configuration and mission  of Azerspace-2. 
Task 10 – Developmental Impact 
The  Contractor  shall  report  on  the  potential  development  impact  of  the  project  in  Azerbaijan 
as  well  as  other  countries  to  be  served  by  the  satellite.  The  Contractor  shall  focus  on  what  the 
economic  development  outcomes  will  be  if  the  project  is  implemented  according  to  the  Study 
recommendations.  While  specific  focus  should  be  paid  to  the  immediate  impact  of  the  project, 
the  Contractor  shall  include,  where  appropriate,  any  additional  developmental  benefits  to  the 
project,  including  spin-off  and  demonstration  effects.  The  Contractor's  analysis  of  potential 
benefits  shall  be  as  concrete  and  detailed  as  possible.  The  development  impact  factors  are 
intended to provide the project's decision-makers and interested parties with a broader view of the 
project's potential effects of the Azerspace-2 satellite. 
The Contractor shall provide estimates of the project's potential benefits in the following areas: 
A.
 
Infrastructure. The Contractor shall provide a statement on the infrastructure impact giving a brief 
synopsis. 
B.
 
Human Capacity Building. The Contractor shall assess the capacity of the Azercosmos organization to 
implement and market the satellite program; address the number and type of positions that would be 
needed to implement the Project; and, identify opportunities for training that will augment existing 
Azercosmos capacity. 
C.
 
Technology Transfer and Productivity Enhancement. The Contractor shall provide a description of any 
advanced technologies that will be implemented as a result of the project and a quantitative description 
of any efficiency that will be gained. 
D.
 
Social Benefits. The Contractor shall identify social benefits of the project that arise from the Project. 
E.
 
Other. The Contractor shall identify any other developmental benefits of the Project.  
Task 11 – Implementation Plan 
The Contractor shall prepare a detailed Implementation Plan designed to provide for procurement, 
financing, construction, launch and operation of the Azerspace-2 satellite in a timely and in a cost-
effective manner. The Implementation Plan shall establish sequence of tasks, assign responsibility 
for  each  task,  and  determine  corresponding  time  limits  for  their  completion.  The  Implementation 
Plan shall target a launch date of not later than the end of calendar year 2016. 
Task 11 Deliverable:  
The Contractor shall provide a copy of the Implementation Plan to the Grantee and incorporate any 
feedback from the Grantee into the Plan, incorporating a final draft into the Final Report. 
Task 12 – Final Report 
The  Contractor  shall  prepare  and  deliver  to  the  Grantee  and  USTDA  a  substantive  and 
comprehensive final report of all work performed under these Terms of Reference (“Final Report”) 
in accordance with Clause J of Annex II. The Contractor shall ensure that the front cover of every 


FINAL REPORT: DEFINITIONAL MISSION TO AZERBAIJAN: 
AZERCOSMOS – AZERSPACE-2 FEASIBILITY STUDY 
August 07, 2013 
Space Partnership International 
63 
 
Final Report contains the name and logo of the Grantee.   
The Final Report shall be organized according to the above tasks, and shall include all deliverables 
and documents that have been provided to the Grantee. The Final Report shall include an executive 
summary discussing the project, the key findings of the Study, and the recommendations for further 
development of project, to be included in the Final Report. In addition to the copies of the Report 
that shall be provided to USTDA, the Contractor shall provide six (6) copies of the public version 
of the Final Report and six (6) copies of the Confidential Version to the Grantee.   
The  Contractor  shall  ensure  that  the  label  affixed  to  the  front  of  the  CD-ROM  also  contains  the 
name and logo of the Grantee. 
 
 
 
 




FINAL REPORT: DEFINITIONAL MISSION TO AZERBAIJAN: 
AZERCOSMOS – AZERSPACE – 2 FEASIBILITY STUDY 
 
August 07, 2013 
Space Partnership International 
Page 66 
 
 
APPENDIX 
Appendix 2: Azerbaijan Key Indicators 
38  
 
 
 
                                                      
38
 The Global Information Technology Report 2010–2011 © 2011 World Economic Forum 


FINAL REPORT: DEFINITIONAL MISSION TO AZERBAIJAN: 
AZERCOSMOS – AZERSPACE – 2 FEASIBILITY STUDY 
 
August 07, 2013 
Space Partnership International 
Page 67 
 
 
 
 


Yüklə 7,43 Kb.

Dostları ilə paylaş:
1   ...   26   27   28   29   30   31   32   33   34




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə